http://www.bundesnetzagentur.de/SharedDocs/Downloads/EN/BNetzA/PressSection/ReportsPublications/2011/110527PressConferenceNuclearPowerMoratoriumpdf.pdf?__blob=publicationFileAs a consequence of lack of these capacities, the market (via trade transactions
and renewable energy feed-in forecasts) in many hours gives rise to a situation,
i.e. a generation dispatch pattern, which does not allow for a (n−1) secure network
operation. (A (n−1) secure operation implies that the network can still be operated
in a stable manner in the event of failure of an essential operating facility. Such
precaution is necessary as these failures are not uncommon.)
The TSOs must therefore correct the market result through increase use of their
instruments such as network switchings, counteracting transactions
(countertrading, SiV1, redispatch) and other interventions in power plant
operation (instruction to provide reactive power, postpone maintenance, reactivate
cold reserves, feed-in management of renewable energy generators).
Load management measures (i.e. controlled disconnection of load) could be
avoided so far.
As a consequence, the original objective of competition-driven market results is
replaced by a more or less centrally controlled planning approach.
This is dubious in terms of energy economics, economically inefficient and
ecologically harmful, but must be accepted for a transitional period and is
unavoidable at the moment.
http://www.bundesnetzagentur.de/cln_1911/SharedDocs/Pressemitteilungen/EN/2011/110831PressConfNuclearPlantBack-upOperation.html?nn=48242BNetzA is relying on extended operation for some older coal plants, some old ones placed in reserve operation, and hopefully Datteln 4 coming online in 2012-2013:
In this connection the Bundesnetzagentur wishes to refer particularly to the need to give top priority to completing the 380 kV very high voltage line from Hamburg/Krümmel to Schwerin. Urgent demand for this line was identified in the legislation, in the Power Grid Expansion Act (EnLAG) of 2009. And finally, the Bundesnetzagentur urges approval of continued operation of Datteln 1 to 3, pending completion of Datteln 4. Delay to Datteln 4 going live may mean that Deutsche Bahn AG's energy requirements in winter 2012/2013 will have to be met from southern Germany, adding to the strain on the transmission networks. The willingness of the government of federal state North Rhine-Westphalia to enter into a dialogue on this is expressly welcomed by the Bundesnetzagentur.
In light of the difficult situation regarding generation in southern Germany in winter 2012/2013 as well, the Bundesnetzagentur would also advise using the experience gained in the coming winter to see whether reserve operation of the Staudinger 3 plant is possible beyond the given closure date of 31 December 2012 until 31 March 2013 at least, as this could ease the situation.