TEPCO: Years needed to remove damaged nuclear fuel
The operator of the Fukushima Daiichi nuclear power plant says it may take a number of years to remove damaged nuclear fuel rods from the Number 1 reactor.
The Tokyo Electric Power Company announced on Saturday, that most of the fuel rods in the Number 1 reactor have melted and fallen to the bottom of the reactor where they are submerged in water.
TEPCO announced in April that it was aiming to get the reactor stabilized and cooled down in 6 to 9 months.
However, no timeline has yet been proposed for the removal of the nuclear fuel.
The company plans to study measures taken at the 1979 Three Mile Island accident in the US, where a meltdown of nuclear fuel rods also occurred. There it took almost 10 years to remove melted fuel at the bottom of the reactor, which resembled hardened lava.
Sunday, May 15, 2011 08:57 +0900 (JST)
http://www3.nhk.or.jp/daily/english/15_05.htmlMore great news from TEPCO:
Rapid meltdown in No.1 reactor
Tokyo Electric Power Company, the operator of the Fukushima Daiichi nuclear power plant, says most of the fuel rods in the No.1 reactor had dropped to the bottom of the pressure vessel within 16 hours of the earthquake on March 11th. The utility revealed its study on the subject on Sunday.
TEPCO said it analyzed the data and calculated a timeline for the developments in the No. 1 reactor on the assumption that the reactor lost its cooling system as soon as it was hit by the tsunami. The firm said that within about 3 hours after the reactor automatically shut down, the cooling water had evaporated to a level at the top of the rods.
In the next hour and a half, parts of the fuel rods are believed to have begun melting.
The temperature of the fuel rods is believed to have reached 2,800 degrees Celsius at this stage, and the meltdown advanced rapidly...
Sunday, May 15, 2011 23:29 +0900 (JST)
http://www3.nhk.or.jp/daily/english/15_21.html